Project NameProject DescriptionProjected Investment 

Tweed South

new zone substation

Establish a new zone substation, install 2km of 66,000 Volt underground cable and reconfigure the existing 11,000 Volt network. More$14 million

Lismore to Mullumbimby

upgrade of power supply

Upgrade of power supply between Lismore and Mullumbimby to cater for increased demand and improve supply quality and reliability. More$70 million

Koolkhan to Maclean

new transmission line

New transmission line from Koolkhan to Maclean to strengthen network security and cater for existing and future demand in the Lower Clarence Valley. More$8 million

Mallanganee

zone substation refurbishment

Install modular 33,000/11,000 Volt kiosk substation.$1.3 million

Iluka town

new powerline

Construct 11,000 Volt distribution powerline including 2.2km of underground cable between Yamba and Iluka under the Clarence River.$3.8 million

Grafton Pound St

underground interconnection

Installation of 600m of 11,000 Volt underground cable and 3-way switching station.$308,000

Lismore

CBD substations/switchrooms refurbishment

Refurbishment of distribution substations/switchrooms in the Lismore CBD. Stage 2 includes the replacement of 1km of overhead copper powerline in the CBD.$824,000

Ewingsdale

Midgen Flat powerline connection

Replacement of existing 11,000 Volt distribution powerline sections and construction of new 4km overhead section to create a tie.$440,000

Ewingsdale

upgrade of existing zone substation

Upgrade the existing 66,000/11,000 Volt zone substation.$9.1 million

Maclean

zone substation refurbishment

Refurbish the existing zone substation to cater for long term load growth.$4.2 million

Grafton North

new 66,000 Volt powerline switchbay

Install a new 66,000 Volt switchbay and connect existing teed powerline.$670,000

Tweed Region

powerline differential protection

Install a new high speed protection system utilising fibre optic cables between zone substations − a first for Country Energy in this region.$250,000


Major sponsorships
  • The landmark 25th anniversary Primex.
  • Wilsons Creek Huonbrook Landcare Group.
  • Friends of the Koalas Group, Lismore.
  • 2009 Country Energy Casino Beef Week.
  • Tweed Business Excellence Awards.
  • 2009 Brunswick Heads Kites and Bikes Festival.
Regional General Manager
Richard Wake
122 Queen Street
Grafton NSW 2460
Tel: 02 6643 7780
Mob: 0417 251 752 

Manager Community Relations
Mike Hely
Tel: 02 6643 7783
Mob: 0427 108 089



Reduce the SizeIncrease the SizePrint this page


Tools

  Search: